The Architect retained by the LA
Department of Water and Power (DWP) to design their new office building/Data Center had
their Mechanical Engineer in place and a nearly completed design when the Principals of
our firm were retained by the DWP to be their
Mechanical System Architect, evaluate the system, and redesign it as required, working
with the Architects team.
The original
design had two 750 ton chillers dedicated to the data center, and three 1250 ton chillers
dedicated to the office tower, there were no interconnections between the two chilled
water systems. In addition to the large
chiller systems, there was approximately 6 MW of electric boilers installed to heat the
office portion of the facility.
After our
evaluation and redesign, the two chilled water loops were interconnected, the chiller
capacity was reduced by 40%, chilled water based Thermal Energy Storage (TES) was
installed, the chilled water system temperature differential was doubled from 12°F to
25°F, a centrifugal heat-pump chiller was
used to take heat out of the data center and TES system and heat the building through the
use of a hot water TES system. The electric
boiler capacity was reduced by over 70%, and relegated to standby duty.
As with all
data centers, the cooling system must have 100% uptime, year-round.
The TES
system and alternate design strategies reduced energy consumption by approximately 23%,
while reducing peak electrical demand by approximately 2.5 MW during the summer, and over
5MW during the winter. |