The third time was the charm for these
facilities. The 600 Corporate Point facility was originally designed and installed
with a low temperature air and ice storage (ice harvester) combination. Water at
34°F was supposed to be available to be pumped through very undersized cooling coils to
cool the air to 50°F to provide cooling to the tenants. After this system failed,
the previous owner performed a retrofit that eliminated the ice storage, added chillers
designed for 35°F chilled water production, and converted the ice storage tanks to an
empty-tank chilled water storage system.
This second
system proved incapable of meeting the needs of the tenants, with a substantial number of
controls and mechanical failures that mandated an engineer be on site whenever a tenant
was in the facility. This would not normally be a problem, but the major tenants in
this facility operate from 6:00 AM to Midnight Monday through Friday, 8:00 AM through
Midnight Saturday, and 8:00 AM through 6:00 PM Sunday. The operating expenses
were killing the facility, as they could not be completely recovered from the tenants due
to the lease agreements made by the previous owner.
In an
attempt to meet the cooling requirements of the tenants, both chillers, plus the TES
system had to be run whenever the ambient conditions were over approximately 73°F,
or if it were humid outside. The fan systems were providing 58°F to 64°F supply
air to the spaces, the face velocity across the cooling coils was in excess of 600 FPM,
and the condensate was being carried off the coils horizontally into the fans. Thus,
even with both chillers and the TES system operational and serving only one building, the
tenants needs were not being met.
The building
next door, 400 Corporate Point, was equipped with water cooled floor by floor self
contained Direct Expansion compressorized systems, operating in excess of 1.0 kW per ton
delivered. The fan systems were undersized, the cooling tower was undersized and in
need of replacement and the compressors and condensers were beginning to fail on a regular
basis.
ROI teamed
up with Control Air Conditioning Service Corporation to compete for this project.
Once again, the ROI solution was deemed to be the most viable and financially strongest
option evaluated by the owners in-house engineering and operations team.
Our team
replaced the cooling coils in both buildings (chilled water and DX) with new chilled
water cooling coils capable of providing a 32°F to 34°F (measured during the summer)
chilled water temperature differential. The TES system was converted to a stratified
chilled water design, with headers designed by ROI, and a new Siemens DDC system was added
to control the new equipment, as well as the air handling equipment in both buildings.
There was no
new refrigeration equipment added to the buildings, and over 500 tons of DX compressor
capacity was removed from 400 Corporate Point.
By carefully
engineering the solution, our Team was able to convert a chiller plant/TES system that was
undersized for one building, into a system that has proven capable of meeting the needs of
two buildings.
After
accounting for energy efficiency incentives, this project should deliver a simple payback
of three to four years. |